3.15.23: The Village at M-22 Update

CRESCENT DRIVE Walls are poured on lots 7, 43, 44.

 

Framing has begun on lot 41.

 

Backfill is finishing up on lot 42 and next up will be framing.

 

Lot 1 flooring is complete, cabinets are installed, and tile is finished in the master shower!

OTTAWA DRIVE Lot 1 is finishing up with the final touches.

 

Lot 7 is being painted, cabinets, countertops and tile have gone in.

 

AND finally, lot 3 is framed, rough HVAC and plumbing are complete and the electrician has begun his work.